The Big Slide is today, and instead of being in Madison, Ind., or Milton, Ky., I'm stuck here in West Virginia trying to earn enough money to make my next car payment. Here's what the folks at the Milton-Madison Bridge Project e-mailed out yesterday. Text and photos are taken directly from the e-mail. Enjoy.
###
It’s the largest bridge slide of its type in North America. The new
Milton-Madison Bridge, which spans nearly a half-mile and weighs some 30 million
pounds, will slide 55 feet laterally from its temporary piers and onto
refurbished permanent piers.
The slide, scheduled to begin Wednesday morning, April
9, could take up to 16 hours before the bridge rests in its final location – on
top of the refurbished piers that held the old Milton-Madison Bridge in place
beginning in 1929. The Coast Guard will close the river during the
slide.
“We’re making history in Indiana and Kentucky,” said Karl
Browning, commissioner of the Indiana Department of Transportation. “Through
hard work and creative engineering, we’ve been able to rebuild this bridge
quickly and cost effectively.”
Pulling a half-mile structure weighing 30
million pounds a distance of 55 feet in a matter of hours is an engineering
marvel, though simple in concept.
Polished steel sliding plates are
secured on top of the refurbished piers. Steel cables and hydraulic jacks
controlled by computers will be used to pull the bridge. A total of eight jacks
are mounted on the piers. Industrial lubrication is put on the sliding plates to
grease the skids. Then, through a series of grabs and pulls, the bridge is slid
into place. Each grab and pull is expected to move the bridge
20–22 inches – up to 10 feet per hour.
Once the bridge
is in its final position, additional work has to be completed before it can
reopen, including inspections, welding and bolting it in place, reconnecting the
driving surfaces, installing expansion joints, pouring concrete, configuring
drainage and re-striping.
“Everyone is a winner on this project,” said
Mike Hancock, secretary of the Kentucky Transportation Cabinet. “We’re showing
the rest of the country how two states, by strategically working together, can
deal with aging infrastructure in creative ways that improve safety and better
the quality of life for their citizens.”
All schedules are
tentative because weather and other factors can alter the schedule. If
all goes as planned, the bridge will reopen to traffic about a week after the
slide.
The new steel truss bridge is 2,428 feet long and
40 feet wide with two 12-foot lanes and 8-foot shoulders – twice as wide as the
old bridge. A 5-foot-wide cantilevered sidewalk will be added to the structure
in the coming months after the slide.
The Milton-Madison Bridge Project
– a joint effort between the Indiana Department of Transportation and the
Kentucky Transportation Cabinet – has received numerous awards. It was named one
of the top 10 bridge projects in the country by Roads & Bridges
magazine, received a 2012 Best of What’s New Award from Popular
Science magazine and received several state and national engineering awards
for innovation. For more information, visit http://www.MiltonMadisonBridge.com or follow the
project on Twitter.